COVID-19’s Impact on Contract Disputes
The COVID-19 pandemic has raised these and countless other questions. The answers are not clear. However, there are three legal concepts that help shed light on the situation. Here’s what you need to know about force majeure clauses, contractual impossibility, and the frustration of purpose doctrine.
There are three types of force majeure provisions that may provide guidance with respect to the COVID-19 pandemic.
- Some provisions specifically mention pandemics, epidemics, or disease outbreaks, though this language is relatively rare. If a contract does contain pandemic language, that may resolve the liability issue.
- Many force majeure provisions mention “Acts of God,” which generally mean natural hazards outside of human control, such as earthquakes, hurricanes, or tornados. Tennessee courts have held that “Acts of God” include floods, falling trees caused by strong storms, and lightning strikes, but other more ordinary and predictable weather events such as heavy rains and icy roads are not covered. Given the nature of the pandemic and the accompanying shut down, it is unclear if a court would treat the COVID-19 pandemic as a natural force, or see the shutdown accompanying the pandemic as human action, which may fall outside of the definition of “Acts of God.”
- Some force majeure provisions reference “Acts of Government” or government regulations and orders, which might provide an avenue for relief. In such a case, even if the COVID-19 pandemic itself is not considered an “Act of God,” a government order to shut down a business may nonetheless create a force majeure event impacting contractual liability.
When a contractual obligation cannot be fulfilled because of unanticipated events, this can be referred to as a situation of “impossibility” or “commercial impracticability.” For example, if a tornado destroys a building where an apartment is located, it is impossible to lease the space. If an apartment suffers heavy water damage, however, it may still be possible to lease the space, but it may be essentially worthless or impracticable to do so. Because the concepts are quite similar, they are often referred to together as an “impossibility defense.” In Tennessee, courts generally will not allow a party to assert an impossibility defense if the situation causing the impossibility was foreseeable.
Like the impossibility defense, the frustration of purpose doctrine requires a party to show that an unanticipated circumstance has fundamentally changed the contract from what was reasonably to be expected by the party to the point that the value of the performance is virtually destroyed. One example might be if a government regulation has changed what the parties are legally able to do.
Given the shutdowns due to a combination of widespread illness and new regulations, many people and businesses in contractual relationships may claim that they should be released from liability, and their claims will likely involve impossibility or frustration of purpose defenses. Resolution of these issues will often involve having a court determine whether the contract remains legally binding.
In the meantime, if you have a contract that has been breached or is facing a potential breach, you should review it carefully—especially any force majeure provision—to see if it might have language that could be interpreted to address the COVID-19 pandemic and shutdown. You also should consider whether your circumstances might support an impossibility or frustration of purpose defense. If any of these situations apply, you may need to provide notice to alert the other party to your contract. Additionally, going forward, we suggest that you work with your legal advisor to consider including appropriate force majeure definitions in your contacts to protect you in your future transactions.
Auto Insurance Statutes Unclear Where Rentals are Concerned
Renting a car can be complicated. Unwinding the insurance issues when a rental in involved in an accident requires untangling the intersection of state and federal law. A new Tennessee Supreme Court ruling gives some guidance. read more
Injured Patron Can’t Sue; Membership Agreement Waived Right
An exculpatory clause waives the right to sue. A recent Court of Appeals case shows that it the waiver can be far broader than you may realize. read more
Legal Malpractice Case Reinstated; “Savings Statute” Applies to Tolling Agreement
The Tennessee Supreme Court recently issued its opinion in Circle C Construction, LLC. v. D. Sean
Nilsen, resulting in the reinstatement of a professional negligence case against a law firm (commonly referred to as a “malpractice” claim). The question in the case was whether a tolling agreement regarding the filing of suit precluded the later use of the “savings statute” that allows plaintiffs to re-file claims within a year after they are dismissed. The Supreme Court determined that, in the absence of contractual language barring the savings statute, the plaintiffs were entitled to rely on it.
DPBC attorneys Donald Capparella and Elizabeth Sitgreaves were counsel of record on behalf of prevailing party Circle C. Construction.
Read the Tennessee Courts’ write-up here (which includes links to the opinion).